Page 30 - Layout 1
P. 30

RV0322.qxp_Layout 1  3/2/22  7:07 PM  Page 28





                      Tarpon River Restoration


                     Project Update






                                            By William Kirk, RVCA Board Member



                     s we enter into the month of March, the Rio Vista  project, and the project should take as long as seven weeks to
                     community approaches the final steps of our    complete. The execution of the dredging operation includes
              Arecovery from the December 2020 sewer pipe           the installation of tension cables stretched across the canal that
              breach. In March/April, the City expects to begin its project   will be dangerous for passing vessels, along with material
              to dredge much of the remaining sediment from the     barges transporting dredged material in a very narrow canal
              neighborhood’s sewer pipe spill into the Tarpon River. The   waterway. These dredging barges will require a full right of
              project will focus on an estimated impact area of 400 feet   way when moving excavated material. Accordingly, the
              with an additional 200 feet of buffer on both sides bringing   Contractor and City have provided the following guidance to
              the total area of dredging to 800 feet, approximately 100   residents of the community regarding the project:
              feet just west of the 9th Ave. bridge, and 700 immediately   • During the length of the project, private boat and vessel
              east of this section.                                 movement will be held to a minimum.
              The performance of the contract work will be executed by   • Due to the required hydraulic dredge methodology, the
              Arbor Tree & Land, Inc. (ATL), who was awarded the contract   canal will be permanently closed and there will be no local
              by the City in the fourth quarter of 2021. The contractor   boat traffic permitted during the weekdays or dredging hours.
              expects to utilize a number of on-water barges to execute the                                                                  (cont. pg. 30)
















































          28                                     rio vista civic association • www.riovistaonline.com
   25   26   27   28   29   30   31   32   33   34   35