                  he rest of the project is on hold as we evaluate both the  Blvd and ends at 17th just west of the Causeway. It will be
                  construction and bond markets. We believe better  a two lane road, one lane in each direction, with generous
              T conditions in both markets than currently exists will save  shoulders to accommodate incapacitated vehicles.
              us some money on the base project costs and allow us to  As opposed to being a flyover (elevated) roadway, the road
              better enhance the final project. We recently provided a site  will be primarily at normal street level. It will have two small
              plan to the City DRC, which is available on the City's website.  bridges along the route to accommodate cross traffic within

              Regarding the bypass road, the new Port bypass road is  the Port. The resulting design will maintain all current Port
              being designed to follow the originally proposed route from  traffic patterns, with only one small change to a service
              several years ago. Heading east and starting at the   road access point.
              intersection of Federal Highway and Spangler Blvd/24th  New travel lanes are being added to the north end of
              Street (across from State Rd. 84), it connects to Eisenhower  Eisenhower Blvd in both directions to accommodate the